The Energy Storage Report 2024

Now available to download, covering deployments, technology, policy and finance in the energy storage market
Premium

Regulator quashes ERCOT’s proposed state-of-charge rules for BESS

LinkedIn
Twitter
Reddit
Facebook
Email

The Public Utility Commission of Texas has ordered the state’s grid operator ERCOT to rescind state-of-charge (SOC) rules requiring batteries to hold additional capacity to provide ancillary services.

The Commission ordered ERCOT to remove its proposed NPRR (Nodal Protocol Revision Request) 1186 in a letter last week (18 January) signed by the Commission’s interim chair and two of its four commissioners.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

By codifying a temporary rule, NPRR 1186 would have meant battery energy storage system (BESS) resources on the ERCOT grid would need to hold – operators argued – more capacity than required when providing ancillary services (such as ERCOT Contingency Reserve Service, Reg-Up and Reg-Down, Responsive Reserve Service or spinning reserve).

The rules also meant BESS technology was having its energy supplies monitored and mandated in real-time in a way no other resources are. Operators said it was an unnecessary limitation on their ability to operate considering penalties already exist for failing to provide contracted ancillary services, for all types of resources including batteries.

Although the Commission’s commentary on NPRR 1186 and its reasons for rejecting it are not on its filings register, commissioner James Glotfelty was quoted in local press saying:

“This presentation that ERCOT put together shows me one thing, really, and that is that every resource fails. So, singling out ancillary services providers of battery storage is discriminatory. Gas plants fail. Nuclear plants fail. Coal plants fail.” 

Companies that submitted filings opposing NPRR 1186 in the lead-up to the Commission’s decision last week were BESS operators Engie, Aypa Power, Eolian and Plus Power (co-filed) and Jupiter Power, as well as environmental organisation Sierra Club. Others that commented earlier in the stakeholder process opposing include operators Spearmint Energy and Key Capture Energy and energy trader Aspire Power.

The only filing in support of NPRR 1186 was oil and gas major Shell, which operates thermal power plants in the state (alongside some BESS). Thermal power plants were historically the main provider of ancillary services, but have increasingly been displaced by BESS which are faster-reacting, cheaper and (obviously) less polluting. ERCOT expects the capacity of BESS on its grid to grow to 9.5GW by October 2024.

Read all the filings related to NPRR 1186, including the companies’ letters opposing or supporting it, and the Commission’s final decision, on its website here.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 19-20 March 2024 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

Read Next

Premium
March 26, 2024
The issue of ensuring reliability of BESS resources in the Texas electricity market has not gone away for grid operator ERCOT, despite the state regulator’s recent quashing of proposed minimum state-of-charge (SOC) rules.
March 26, 2024
Canada utility Hydro-Quebec’s BESS technology arm EVLO Energy Storage has prioritised safety and quality while compromising on energy density, executives told Energy-Storage.news.
March 21, 2024
According to Wood Mackenzie, energy storage deployment numbers in the US broke records for three successive quarters with previous records “shattered” to finish the year.
March 20, 2024
The right balance between battery health and profitability is essential for success, writes Laura Laringe, CEO of reLi Energy.
March 19, 2024
Battery storage developers and operators discussed the challenges and opportunities in the US market, on the first day of Solar Media’s Energy Storage Summit (ESS) USA 2024.

Most Popular

Email Newsletter